Confirm the site and service schedule
Start with the opening date, building access, vendor lead times, and the person who can make or approve technology decisions for the location.
- Confirm the opening date, move-in sequence, address, suite details, and building access rules.
- Order internet and phone service early enough for the provider's lead time and installation.
- Name the project owner and list the internet, phone, security, landlord, and hardware contacts.
- Record what the landlord or building supplies and what your company must buy or set up.
Prepare the employee workspace
Test the office with the devices and tasks employees will actually use. A provider handoff is not the same as a working leasing desk.
- Prepare workstations, monitors, docks, chargers, printers, scanners, phones, and accessories.
- Set up employee accounts, email, shared mailboxes, calendars, files, sign-in security, and property application access.
- Set up business Wi-Fi and any separate guest or resident network the building requires.
- Test printing, scanning, calls, video meetings, shared files, sign-in, and leasing tasks from each desk.
Document the day-one handoff
A short handoff record keeps the office supportable after opening and shows what is still unfinished.
- Save provider tickets, circuit details, equipment inventory, warranties, account owners, and vendor contacts.
- Record Wi-Fi, printer, phone, device, and application details in the approved documentation location.
- List each open issue, workaround, and dependency with an owner and a follow-up date.
- Schedule a review once the team has worked in the office under normal conditions.
Leasing-office opening worksheet
Use this worksheet at a walkthrough before the first tour or appointment. Assign an owner and date to each row, record whether the test passed, and document who will resolve any issue that could delay opening.
| Requirement | Suggested owner and timing | Acceptance test |
|---|---|---|
| Internet and staff Wi-Fi | Network lead after ISP installation | Connect a staff device in the office and open the services staff need. Record the circuit reference and support contact. |
| Staff accounts and MFA | IT and the leasing manager before first use | Have an approved staff member sign in from a leasing workstation and complete multifactor authentication. |
| Shared mail and files | Microsoft 365 or Google Workspace administrator before handoff | Open the shared mailbox and the team's files with the permissions required for a normal shift. |
| Leasing software | Leasing manager with the software owner before go-live | Complete a representative leasing workflow using an approved test record. Confirm any permissions or vendor escalations. |
| Printers and scanners | Site contact after devices join the network | Print from each required desk and scan to the approved destination. Confirm a test page does not expose resident information. |
| Phones and voicemail | Phone owner after the provider confirms activation | Place and receive a test call using the public leasing number. Check voicemail routing and who receives alerts. |
| Vendor and support handoff | Project owner before opening | Confirm staff can open a support request. Record vendor contacts, open issues, named owners, and follow-up dates. |
- Test from the actual office with approved staff accounts and test data.
- Use the notes column for ticket references and outcomes. Store credentials through your approved process.
Questions to ask
How far ahead should IT planning start for a new leasing office?+
Start as soon as the opening date and site are known. Internet installation, building access, hardware delivery, and vendor scheduling can set the timeline.
What must work before the office opens?+
At minimum, internet, Wi-Fi, user sign-in, email, shared files, printing, phones, and required applications must work. Test them, and the actual leasing tasks, before opening.
Can the office open before every improvement is complete?+
Sometimes. Separate day-one requirements from later improvements, write down the remaining risk, and give each deferred item an owner and a date.